TIMELINE: Key dates in the history of the Trans Mountain pipeline

From 1953 to 2018, the Trans Mountain pipeline has been the way of transporting oil from Alberta to B.C.

Here are some key dates in the history of the Trans Mountain pipeline and Kinder Morgan Canada’s efforts to expand its capacity:

October 1953: The Trans Mountain pipeline begins shipping oil with an initial capacity of 150,000 barrels per day. The project features four pump stations along its 1,150-kilometre route and a marine dock that connects loading facilities on the east side of Edmonton with ocean tankers in Burnaby, B.C.

1957: Pipeline capacity is expanded via the construction of a 160-kilometre pipeline loop. The Westridge Marine Terminal is built and commissioned in Burnaby

Jan. 14, 1985: Trans Mountain’s biggest spill occurs at a tank farm in the Edmonton area. Nearly 10,000 barrels of oil are released.

2006 – 2008: The Anchor Loop project adds 160 kilometres of new pipeline through Jasper National Park and Mount Robson Provincial Park between Hinton, Alta., and Hargreaves, B.C. The extension includes 13 new pump stations and modifications to existing stations, increasing capacity from 260,000 bpd to 300,000 bpd.

Feb. 21, 2012: Kinder Morgan says it wants to expand the Trans Mountain pipeline after receiving support from oil shippers and will begin public consultations.

Dec. 16, 2013: An application is made to the National Energy Board (NEB) to expand the Trans Mountain pipeline. Construction is proposed to begin in 2017, with the aim of having oil flow through the expansion by December 2019.

November 2014: More than 100 people are arrested after they camp out in a conservation area on Burnaby Mountain, east of Vancouver, to block crews from conducting drilling and survey work related to the pipeline expansion. Most of the charges are later dropped.

READ MORE: Pipeline supporters rally across B.C.

READ MORE: Rival protests highlight B.C.’s divide over pipeline project

August 2015: The NEB postpones public hearings after striking from the record economic evidence prepared by a Kinder Morgan consultant who was to begin working for the regulator.

Jan. 12, 2016: Alberta Premier Rachel Notley says in a written submission to the NEB that the Trans Mountain pipeline expansion is in the best interests of both Alberta and Canada.

Jan. 27, 2016: The federal Liberal government says pipeline projects such as the Trans Mountain expansion will now be assessed in part on the greenhouse gas emissions produced in the extraction and processing of the oil they carry. Proponents will also be required to improve consultations with First Nations.

May 17, 2016: Ottawa appoints a three-member panel to conduct an environmental review of the Trans Mountain expansion project.

May 29, 2016: The NEB recommends approval of the pipeline, subject to 157 conditions, concluding that it is in the public interest.

Nov. 29, 2016: Prime Minister Justin Trudeau sanctions the Trans Mountain expansion, part of a sweeping announcement that also saw approval of Enbridge’s Line 3 pipeline replacement but the end of its Northern Gateway project.

Jan. 11, 2017: B.C. Premier Christy Clark announces her support for the project, saying Kinder Morgan has met five government conditions including a revenue-sharing agreement worth up to $1 billion.

May 15, 2017: The Federal Court of Appeal grants Notley’s government intervener status in a lawsuit filed by municipalities and First Nations against the project.

May 25, 2017: Kinder Morgan makes its final investment decision to proceed with the development, now estimated to cost $7.4 billion, subject to the successful public offering of Kinder Morgan Canada.

May 29, 2017: The B.C. NDP and Greens agree to form a coalition to topple the Liberal party, which won a minority government in an election earlier in the month. The parties agree to “immediately employ every tool available” to stop the project.

May 30, 2017: Kinder Morgan Canada debuts on the Toronto Stock Exchange after a $1.75-billion public offering.

June 29, 2017: The B.C. Liberals lose a no-confidence vote, clearing the way for NDP Leader John Horgan to become premier.

Aug. 10, 2017: The B.C. NDP government hires former judge Thomas Berger to provide legal advice as it seeks intervener status in the legal challenges against the project filed by municipalities and First Nations.

Oct. 26, 2017: Kinder Morgan Canada asks NEB to allow work to begin despite a failure to obtain municipal permits from the City of Burnaby.

Dec. 7, 2017: NEB allows Kinder Morgan Canada to bypass Burnaby bylaws.

Jan. 17, 2018: Kinder Morgan Canada warns the Trans Mountain expansion project could be a year behind schedule.

Jan. 18, 2018: NEB establishes a process to resolve permitting issues between Kinder Morgan Canada and provincial and municipal authorities.

Jan. 30, 2018: B.C. government moves to restrict any increase in diluted bitumen shipments until it conducts more spill response studies, a move that increases the uncertainty for Trans Mountain.

March 9, 2018: B.C. Supreme Court grants interim injunction aimed at preventing anti-pipeline activists from protesting construction at two terminals in Burnaby.

March 15, 2018: B.C. Supreme Court grants indefinite injunction preventing protesters from coming within five metres of two work sites for the project.

March 23, 2018: Green Party Leader Elizabeth May and New Democrat MP Kennedy Stewart arrested at a protest against the pipeline expansion; Federal Court of Appeal dismisses a B.C. government bid challenging a NEB ruling that allows Kinder Morgan Canada to bypass local bylaws.

March 27, 2018: City of Burnaby, B.C., says it will file an appeal to the Supreme Court in connection with the Federal Court of Appeal ruling.

April 8, 2018: Kinder Morgan Canada suspends non-essential spending on the Trans Mountain expansion project and sets a May 31 deadline to reach agreements with stakeholders.

May 29, 2018: Federal government announces deal to buy the Trans Mountain pipeline and expansion project from Kinder Morgan Canada for $4.5 billion.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Provincial COVID-19 data can now be used for B.C. to prepare for a second wave

In the past week, B.C. has seen a slight spike in daily test-positive case counts

Food security groups looking for new home in Campbell River

Grassroots Kind Hearts and other groups looking into alternatives

North Island College receives $125,000 donation from accounting firm

The donation from Chan Nowosad Boates will be used to purchase technology as well to award bursaries for students

Mobile Health Unit takes to Campbell River streets

KDC Health-operated health bus offers holistic approach to health

Vancouver Island business ad unintentionally features OK gesture linked to white supremacy

Innocuous ‘OK’ gesture in cleaning franchise advertisement gets flak on social media for ‘supposedly’ promoting white supremacy

QUIZ: Are you ready for a summer road trip?

How much do you really know about roads, motor vehicles and car culture? Take this quiz to find out.

Mirror business directory and map

If you’d like to be added to the list, shoot us an email

B.C. Ferries increasing passenger capacity after COVID-19 restrictions

Transport Canada 50-per-cent limit being phased out, no current plans to provide masks

Shellfish industry get funds to clean up at Island sites and beyond

Businesses can apply to cover half of costs to clean up so-called ‘ghost gear’

Amber Alert for two Quebec girls cancelled after bodies found

Romy Carpentier, 6, Norah Carpentier, 11, and their father, Martin Carpentier, missing since Wednesday

B.C. man prepares to be first to receive double-hand transplant in Canada

After the surgery, transplant patients face a long recovery

Grocers appear before MPs to explain decision to cut pandemic pay

Executives from three of Canada’s largest grocery chains have defended their decision to end temporary wage increases

Bringing support to Indigenous students and communities, while fulfilling a dream

Mitacs is a nonprofit organization that operates research and training programs

RCMP ‘disappointed’ by talk that race a factor in quiet Rideau Hall arrest

Corey Hurren, who is from Manitoba, is facing 22 charges

Most Read