Diversion tunnels have been completed to redirect the Peace River during low water this summer, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

Dam has been affected by possible COVID-19 delays

A letter addressed to NDP Leader John Horgan is urging the province to halt the construction of the Site C dam while geotechnical issues are investigated.

The open letter, which includes signatories such as former BC Hydro CEO Marc Eliesen, Chief Roland Willson of the West Moberly First Nations and 16 other former CEOs, scientists and Indigenous leaders, says that the “problem-plagued” project needs to stop construction.

“The Site C project is years away from completion, is mired in problems that may be unfixable, and confronts new, potentially horrendous cost over-runs,” the letter states.

The letter cites geotechnical problems revealed in July, when BC Hydro CEO Chris O’Riley wrote of “a project risk” to do with the right bank. O’Riley said that “investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas.”

The CEO’s letter also cited financial hurdles brought about by the COVID-19 pandemic. Prior to the worldwide health crisis, the first generating unit of the Peace River dam was scheduled to go into service in late 2023, with a final in-service date in 2024.

“While we remain on schedule to achieve river diversion in 2020, there is uncertainty with the project’s schedule and in-service date. This is primarily due to our ability to re-start and accelerate work that was halted due to the pandemic,” O’Riley wrote in July.

Monday’s (Sept. 28) open letter asks the government to “immediately suspend all construction activities at the project” while giving Site C special advisor Peter Milburn, a former B.C. government bureaucrat with a background in civil engineering, time to accomplish three tasks.

The open letter’s signatories want Milburn to appoint a panel of three professionals with no link to Site C to do geotechnical assessment. Secondly, the letter asks for that information to be public prior to the government making a decision to restart the project.

“This is crucial because to date the public’s trust in the Site C project has been eroded by a lack of transparency,” the letter states. The last ask is for the public to get a “full accounting” of the costs to date associated with Site C, as well as of the upcoming costs required to complete the project.

The cost of the Site C Dam was pegged at $7.9 billion in 2011 but has grown to $10.7 billion. The dam has also been the subject of legal battles, with the Prophet River First Nation settling one in early August.

READ MORE: Agreement between province, BC Hydro, First Nation, ends legal fight over Site C

READ MORE: BC Hydro’s Site C set back by COVID-19, foundation changes


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Want to support local journalism during the pandemic? Make a donation here.

CoronavirusIndigenousSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Candice Woloshyn prepares her flower beds for the next season at her ‘Dirty Girl Flowers’ farm in Merville. Despite the pandemic, Woloshyn was able to sustain her homegrown business as community members opted for regular deliveries of fresh cut flowers. Photo by Binny Paul/ Campbell River Mirror.
Vancouver Island flower farmers were blooming as the pandemic wilted everything else

Floriculturists saw increased subscriptions as fresh flowers became a ‘sight for sore eyes’ during isolation

Campbell River's new hospital, July 2018
Nurse diverts opiates and falsifies records at Campbell River Hospital

Nurse facing disciplinary action for moving opiates out of the hospital

The recently acquired Thulin family car, photographed in front of the Willows Hotel in 1912. MCR7453. Courtesy Museum at Campbell River
No license to drive

A Look Back into the History of the Campbell River Area

The Ka:’yu:’k’t’h’/Che:k:tles7et’h’ First Nation will be joining the SRD board as a full member in April, 2021. Photo by Marc Kitteringham, Campbell River Mirror
Island First Nation on track to join Strathcona Regional District board

Representative Kevin Jules says he’s ‘thrilled’ to be a full member of the board

The Museum at Campbell River and Greenways Land Trust are hosting a virtual talk by UVIC PhD candidate Garth Covernton on Nov. 5. Tickets are only $7 and are available at crmusum.ca. Photo courtesy Garth Covernton
New Museum at Campbell River speaker series leads off with talk on microplastics

Tickets for digital event Nov. 5 are only $7 and include the opportunity to ask questions

FILE – Provincial Health Officer Dr. Bonnie Henry provides the latest update on the COVID-19 pandemic in the province during a press conference in the press theatre at Legislature in Victoria, B.C., on Thursday, October 22, 2020. THE CANADIAN PRESS/Chad Hipolito
B.C. shatters COVID-19 records with 817 weekend cases; masks now expected indoors

Three people have died over the past three reporting periods

Dr. Richard Stanwick, Island Health chief medical health officer, immunizes Victoria Schmid, Island Health���s vice-president of pandemic planning. (Submitted photo)
Can’t wait for a COVID vaccine? Get the flu vaccine in the meantime, says Dr. Enns

“We’re in a pandemic, and we can’t afford to have dual viral infections.”

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

The ‘new normal’ for hockey parents in Chilliwack and elsewhere in B.C., watching their kids from outside of the arena due to COVID-19 protocols. (Submitted photo)
Chilliwack hockey parents petition to be let back in the arena

Refused access due to pandemic protocols, parents are now applying pressure to loosen the rules

Aaliyah Rosa. File photo
Crown says murder of B.C. girl, 7, by accused mother was planned, deliberate

The trial of KerryAnn Lewis began Monday in New Westminster

Commissioner Austin Cullen listens to introductions before opening statements at the Cullen Commission of Inquiry into Money Laundering in British Columbia, in Vancouver, on February 24, 2020. THE CANADIAN PRESS/Darryl Dyck
B.C. money laundering inquiry hears of $800,000 and more in bags, luggage, backpacks

The lottery corporation has said it consistently reported suspicious transactions to Fintrac

Most Read