Temporary road under construction at the Trans Mountain terminal in Burnaby to bring in components for 14 additional storage tanks. (Trans Mountain)

Trans Mountain pipeline work proceeds with COVID-19 restrictions

25 km of pipe laid in Alberta, Burnaby tank farm expanding

With half of the 50-km Edmonton-area portion of the Trans Mountain pipeline twinning completed, work is continuing to add 14 storage tanks to its Burnaby terminal and expand the Westridge marine terminal for export of Alberta oil sands crude.

Worksite restrictions for COVID-19 on the project now include temperature testing people entering the sites, staggering work shifts to minimize the number of workers on site, and restricting vehicle transport for physical distance, the now-federally owned Trans Mountain said in a project update this week.

Much of the pipeline twinning work from Alberta to the B.C. border has been completed over the past decade, and nearly 25 km of twin pipe has been laid in the Edmonton area. At the west end of the 67-year-old oil and fuel transportation system, piledriving and construction of the shipping terminal expansion into Burrard Inlet are ongoing.

The expansion project includes a total of 19 more storage tanks, with four at Edmonton one at Sumas, where a branch line has served Washington refineries since 1954.

The marine terminal expansion includes a new dock complex with three tanker berths, to allow the loading of three Aframax-size tankers at once. The expansion includes a utility dock to moor tugboats, boom boats and emergency response vessels, added delivery pipelines and an extension of the land along the shoreline to accommodate new equipment.

The foreshore expansion is being constructed of steel retaining walls, which have been filled with aggregate material and soil to establish the foundation.

At the Burnaby terminal, a temporary road is under construction and the site is being prepared for 14 new storage tanks. The plan includes a tunnel through Burnaby Mountain from the tank farm to the Westridge terminal, big enough to contain three 30-inch delivery pipes to load vessels.

With the only pipeline link between Alberta, B.C. and Washington state oversubscribed and increasing shipments by rail before the current pandemic slowdown and turmoil in the world oil market, the expansion pipe is planned to carry heavy oil for export. The existing line will carry refined fuels, light crude and synthetic crude produced from bitumen at upgraders the Edmonton region.

RELATED: Lack of pipelines costing Canada billions, study finds

RELATED: Trans Mountain expansion cost jumps by 70%

The Justin Trudeau government took over the pipeline in 2018 after Kinder Morgan Canada set a deadline to walk away from the expansion project. The $4.5 billion purchase price came with an estimate of $7.4 billion to complete the expansion, an estimate later raised to $12.6 billion with a completion date pushed to 2022 amid protests and court challenges.

A 2018 study estimated Canada was losing nearly $16 billion in revenue that year due to pipeline bottlenecks that effectively made the U.S. the only customer for new capacity.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC politicsCoronavirusTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Campbell River Board of Education approves $72-million budget

Trustees pleased budget aligns with board’s new strategic plan

NIC leads province in transition to online biology labs

North Island College (NIC) biology faculty are among the first in the… Continue reading

Like father, like son: second generation hockey player joins Campbell River Storm

Wyatt Murray’s father, Ben Murray, played for the team in late 90s

BC Transit rate change, embarking rules shift into action June 1

Campbell River transit system getting a new day pass

Bride thankful ailing stepdad was able to walk her down the aisle

Ceremony held amidst pandemic in order to fulfill bride’s wish to have stepdad give her away

Facing changes together: Your community, your journalists

The COVID-19 pandemic has changed the world in ways that would have… Continue reading

Mirror business directory and map

If you’d like to be added to the list, shoot us an email

COVID-19: B.C. landlords can’t evict if they decline rent assistance

Emergency order ‘incentive’ for federal program, Carole James says

Duncan’s Queen Margaret’s School pioneers thermal imaging in school reopening

Private school is first in B.C. to use new tech post-COVID-19

Investigators probe death of CN employee at Surrey rail yard

Transportation Safety Board is investigating an ‘occurrence that took place during switching operations’

Trans Mountain starts B.C. leg of pipeline twinning project

Mostly finished in Alberta, Burnaby terminal expanding

NDP getting COVID-19 wage subsidy ‘indirectly,’ B.C. Liberal leader says

Andrew Wilkinson says he’s heard no concerns from public

Most Read