Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Campbell River’s Seawalk, trails still open but proper social distancing urged

City issues reminder about safe use of trails and green space

Roadside message of gratitude erected

On her way to work this morning, Lowene Baxandall got a pleasant… Continue reading

Inside Campbell River’s Emergency Operations Centre

Centre dictates how city responds to COVID-19

Campbell River planning desk remains open

Email or telephone only for planning, approval and engineering

‘We will get through this’: B.C. sees new COVID-19 death, but 57% have recovered

A total of 1,066 people have tested positive for the novel coronavirus

Couple celebrates 61st anniversary through Vancouver Island seniors’ home window

Frank and Rena Phillips marked occasion at Nanaimo Seniors Village this week while social distancing

Association launches French-language games, online tools for families learning at home

Games, culture and vocabulary included in new virtual resources

‘There can be no ambiguity’: Travellers brought home to B.C. must self-isolate

Health Minister Adrian Dix said the mandatory isolation must be abided by

B.C. man sick with COVID-19 calls it a ‘horrible disease’

Tim Green says he has ‘extreme coughing fits every hour’ to clear his lungs

Belle from ‘Beauty and the Beast’ entertains home-bound kids in Cowichan Bay

Alora Killam, 16, played the part in musical two years ago

55+ BC Games cancelled amid COVID-19 concerns

Greater Victoria set to host 2021 event

BC Hydro offers three-month bill ‘holiday’ for those affected by COVID-19

Industrial customers can defer half of their power bills

Some April Fool’s Day jokes bring much-needed laughter; others tone deaf to COVID-19

Police are warning the public not to use the ongoing pandemic as a punchline

Most Read