Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

B.C. to move salmon farms out of coastal migration route

Broughton Archipelago plan set to start in spring of 2019

City of Campbell River transit to get some infrastructure help next year

Hint: It’s a bus pullout on Dogwood at Carihi and doubling the rate of bus shelter installation

John Hart Generating Station officially fully operational

Still a few finishing touches, and more more work on the Campbell River system in the coming years

Stranded B.C. trucker writes final wishes before being rescued 3 days later

‘I was just praying someone would come along’

Campbell River School District calls for report on buses and seat-belts

Parents have questions following expose on research around buses and safety

John Hart Generating Station officially fully operational

Still a few finishing touches, and more more work on the Campbell River system in the coming years

Canadians spent almost $64,000 on goods and services in 2017

Households in B.C. each spent $71,001 with housing costs contributing to higher average

Speaker at rally says Alberta oil ‘puts tofu on the table in Toronto!’

RCMP estimated more than 1,500 people attended the rally in Grande Prairie

White House closer to partial shutdown with wall demand

Without a resolution, parts of the federal government will shut down at midnight on Friday, Dec. 21

Canucks score 3 power-play goals in 4-2 win over Oilers

Vancouver sniper Boeser has 6 goals in last 5 games

Microscopic parasite found in Prince Rupert water affecting thousands

More than 12,000 residents affected by the boil water advisory issued Dec. 14

Trudeau lashes out at Conservatives over migration “misinformation”

Warning against the “dangers of populism,” Trudeau says using immigration as a wedge political issue puts Canada’s future at risk.

B.C. hockey coach creates ‘gear library’ to remove cost barrier of sport

Todd Hickling gathered donations and used gear to remove the cost barrier for kids to play hockey.

Canada’s ambassador meets with second detainee in China

Global Affairs says John McCallum, Canada’s ambassador to China, met with Spavor Sunday

Most Read