Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

No danger to Quadra Island residents, says representative for barge parent company

Compressed CO2, corrosion inhibitor among cargo of grounded barge on Quadra Island

Women of rock and roll slide into Campbell River Curling Club

Twelve teams take part in ladies open bonspiel

Increase in property crime is partly preventable, Campbell River RCMP say

While Campbell River RCMP experienced a decrease in files for the period… Continue reading

Campbell River rider takes Island endurocross championship

John Stevenson has only been riding competitively for a handful of years, but he’s already at the top

Vancouver Island substitute teacher said he wanted a student to ‘whack’ two others on Grade 8 field trip

Campbell River teacher-on-call suspended three weeks for November 2018 incident

‘We love you, Alex!’: Trebek gets choked up by ‘Jeopardy!’ contestant’s answer

The emotional moment came in Monday’s episode when Trebek read Dhruv Gaur’s final answer

Birthday boy: Pettersson nets 2 as Canucks beat Predators

Vancouver ends four-game winless skid with 5-3 victory over Nashville

Judge rejects Terrace man’s claim that someone else downloaded child porn on his phone

Marcus John Paquette argued that other people had used his phone, including his ex-wife

Petition for free hospital parking presented to MP Jody Wilson-Raybould

What started as a B.C. campaign became a national issue, organizer said

Petition to ‘bring back Don Cherry’ goes viral after immigrant poppy rant

Cherry was fired from his co-hosting role for the Coach’s Corner segment on Nov. 11.

B.C.’s high gasoline prices still a mystery, Premier John Horgan says

NDP plans legislation this month, seeks action from Justin Trudeau

Group walking on thin ice at B.C. lake sparks warning from RCMP

At least seven people were spotted on Joffre Lakes, although the ice is not thick enough to be walked on

One dead after fiery crash in Duncan

A man has died after a fiery motor vehicle collision Monday night,… Continue reading

VIDEO: Don Cherry says he was fired, not sorry for ‘Coach’s Corner’ poppy rant

Cherry denies he was singling out visible minorities with his comments

Most Read