Site C actions, costs won’t be known until after B.C. election, Horgan says

Peace River diverted for construction of reinforced dam base

The Peace River’s flow is now diverted through twin tunnels for the main riverbed works of B.C. Hydro’s Site C dam, opening a dry area of the riverbed for construction of “foundation enhancements” that were identified by geological mapping as a change to the project in late 2019.

The river diversion proceeded on schedule starting Oct. 2, but the additional work and COVID-19 delays mean the completion date and additional costs remain uncertain, NDP leader John Horgan acknowledged in his final campaign event in Vancouver Thursday.

This week B.C. Hydro announced three positive tests for COVID-19 on the site near Fort St. John, and the start of burning wood debris captured from the river to keep diversion tunnels clear.

Newly sworn in as premier in 2017, Horgan called for the B.C. Utilities Commission to make a rapid review of the project, which by then had $4 billion invested in the long-considered third dam on the Peace River. That review was “inconclusive,” Horgan said, and the NDP government decided to proceed at a projected cost increased by $1 billion to $10.7 billion.

RELATED: Site C dam set back by COVID-19, foundation changes

RELATED: NDP government bails out B.C. Hydro for $1.1B debt

RELATED: After losing at every level, West Moberly sues again

B.C. Hydro’s annual report in July 2020 notified the government and public of the latest problems, including delays due to COVID-19 restrictions on the huge job site as well as the new geological issues. Before calling the election, then-energy minister Bruce Ralston appointed former deputy finance and transportation minister Peter Milburn to assess the project again.

“But now we are three and a half years later, and new evidence that was not presented at that time is being examined by Mr. Milburn,” Horgan said Oct. 22. “This is absolutely serious for Hydro ratepayers and for the project. I don’t want to diminish it in any way. But I don’t know until I hear from the experts what’s the magnitude of the problem, and what steps we need to take to protect British Columbians.”

In a July progress report to the B.C. Utilities Commission, B.C. Hydro CEO Chris O’Riley said the combined effects of COVID-19 and a series of construction issues have pushed the cost up by an amount not yet known. Those included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, as well as the latest of a series of legal challenges from the West Moberly First Nations.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote in a letter to BCUC chair David Morton.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC politicsBC Votes 2020Site C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

The North Island 9-1-1 Corporation (NI911) has supported local residents for 25 years. Black Press file photo
North Island 911 looks to change how they get funding

Three options to be decided upon in early 2021

B.C. will be testing its Alert Ready system on Nov. 25. Black Press Media file
Why some people don’t get emergency alert notifications

Province testing Alert Ready system on Wednesday

Diana deWitt of the Coastal Community Credit Union (right) presents a cheque for $500 to Knight Larry Panich in their ongoing support of the Knights of Columbus Christmas Hamper Fund. Photo contributed
Drop off donations at Campbell River Christmas Hamper Fund depot in Tyee Plaza

It is also one of two places where you can get your Christmas Hamper application

(Village of Sayward)
Sayward elects new mayor and two council members

New mayor-elect Mark Baker and council members will be sworn in on Dec. 1.

Provincial health officer Dr. Bonnie Henry updates B.C.’s COVID-19 situation at the B.C. legislature, Nov. 23, 2020. (B.C. government)
B.C. daily COVID-19 cases hits record 941 on Tuesday

Further restrictions on indoor exercise take effect

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Stock photo
Senior from Gibsons caught viewing child porn sentenced to 10 months

74-year-old pleaded guilty after police seized 1,500-2,500 images

BC Teachers' Federation President Teri Mooring is asking parents of school-aged children to encourage the wearing of masks when possible in schools. (THE CANADIAN PRESS/Chad Hipolito)
LETTER: Teachers union encourages culture of mask wearing in B.C. schools

BCTF President Teri Mooring asks parents to talk with children about wearing masks in school

Prime Minister Justin Trudeau speak to the media about the COVID-19 virus outside Rideau Cottage in Ottawa, Friday, Nov. 20, 2020. THE CANADIAN PRESS/Adrian Wyld
Canada’s inability to manufacture vaccines in-house will delay distribution: Trudeau

First doses of COVID-19 vaccine expected in first few months of 2021, prime minister says

(Pixabay)
All dance studios, other indoor group fitness facilities must close amid updated COVID-19 rules

Prior announcement had said everything except spin, HIIT and hot yoga could remain open

B.C. Liberal interim leader Shirley Bond speaks to reporters from Prince George via Zoom conference, Nov. 24, 2020. MLAs are being sworn in for the legislature session this week, many of them also by video. (B.C. legislature)
B.C. Liberal leadership contest will wait for election post-mortem

Interim leader set to face NDP on payments for COVID-19

Product Care offers more than <a href="http://link.mediaoutreach.meltwater.com/ls/click?upn=pDYyTceU0YgTDdsd92GohdQJsmSiPFEkcB4MdMM0Qkoqb1aJA-2By5aWklKJXV6QRdyTteNjr2FccUOVLUe4t5Zw-3D-3D1ds-_KVyBcpjXADXifSWVpM8nQcAzSm9-2B6fEFnjVrTsOcu31irDHDxi5k0QTOIWCqMXUxaNbrf0yRzXSSpROCkfx3NkUtbr65Dkcw1J0by-2F-2BDdDiJGbcfhtjHWYSs66NwakeCCLYkj20e9ICIZsLcedqNZKBhsN0sGgBsInpdzsddYikUZkmQvFdxLJhakpgAA6aAJ5ScUoWR6vO9sM819vRB-2F6x7dsdfIaWa4ZgHxR4G7hauxgSJCsNI2bP5J62EFfM0aiDqRPwUPUjt7i5-2FMqpdJxrEBewnLky-2B3lE0JAmi5UsJBkJejuLOjsndZz4b7dNgbvt6KyewKuF0sxU2rpYgkAO9YAKc9STuFJd28Qn7jE0-2FqlB8HKOvpW150NHS-2BOMBcK5rkZ8YAuPqJy11k-2BgndiKB-2FWl2icAfbWtRGJPb8fM-3D" target="_blank">150 free drop-off locations</a> in B.C. (Pixabay.com)
Recycling broken or burnt string lights can reduce holiday landfill waste

In 2019, Product Care Recycling diverted more than 11.6 million light bulbs from landfills

Most Read