News

Campbell River trails to be diverted for dam construction

Construction on the John Hart Dam Generating Station has been pushed back a year.

BC Hydro has been deliberating the best option for the aging generating station and now it’s up to the BC Utilities Commission.

The board will give its verdict on the project – that comes with a $1.35 billion price tag – this spring.

If it’s approved, Stephen Watson, spokesperson for BC Hydro, said construction could begin in the summer of 2013. That’s one year later than Watson originally predicted. When he met with city council last March, Watson said BC Hydro would issue a Request for Qualification in spring 2011 and a Request for Proposal that same fall, with construction beginning in late 2012.

However, BC Hydro spent last year re-considering its options. Watson said some of the equipment at the 64-year-old generating station is in poor condition and Hydro was concerned about how it would perform in the event of a moderate earthquake.

The company settled on replacing the wood stave pipeline running from John Hart Lake to the generating station with a two-kilometre long, eight metre in diameter, tunnel. The project also calls for a brand-new generating station, built beside the current facility.

“The BC Utilities Commission will ask a lot of questions about how we arrived at this,” Watson told council on Tuesday, during his fifth presentation to council about the upgrade project. “We looked at the status quo, leaving things the way they are.

“We looked at generating alternatives, stage replacement and even decommissioning options. We moved to the tunnel option because of seismic concerns.”

The upgrades are also designed to erase the ongoing risk and consequence to fish from BC Hydro’s unplanned river flow reductions and to increase the power generation capacity from the current 126 megawatts to 138 megawatts, by using more efficient equipment.

Throughout construction, which is expected to last five years, the river trail near the generating station will be inaccessible for three years and the John Hart Dam to Brewster Lake Road will be closed to traffic for three years.

Watson said there will be road detours in place and BC Hydro will construct a 75-space parking lot off Brewster Lake Road, as well as provide a trail and access to Elk Falls Provincial Park.

BC Hydro is holding an open house Feb. 16 from 3-7 p.m. at the Maritime Heritage Centre to give the public the chance to view the site plans and project details.

“We certainly encourage people to come out and learn more about the project,” Watson said.

To find out more about the project visit bchydro.com/regeneration50 and look under Key projects & initiatives.

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Campbell River Scout receives Award of Valour
 
UPDATE: Divers make new attempt to reach vessel
 
VIDEO: Ottawa hero Kevin Vickers receives standing ovation in House of Commons
Flu shot-or-mask rule upheld by arbitrator
 
Cyclists tout green crossing over ravine
 
Community responds to water trouble
City acts on three nuisance properties
 
Trash trauma at Cobble Hill turnaround riles resident
 
Fantasy becomes a reality at Duncan Comic Book Expo

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 17 edition online now. Browse the archives.